The East Container Terminal (ECT) at the Colombo Port is expected to commence operations at 50% capacity within this month, Deputy Minister of Ports and Civil Aviation Janitha Ruwan Kodithuwakku announced.
The Deputy Minister made this announcement on November 27 during an inspection visit to review the operational progress of the terminal’s automated yard.
He said the Sri Lanka Ports Authority had successfully overcome technical challenges related to completing the semi-automated yard, with Automated Rail Mounted Gantry (ARMG) cranes now operational.
The first operational lane has already commenced operations, while the remaining 10 lanes are expected to be activated within this month.
The terminal has also achieved the expected operational efficiency of handling between 20 and 30 containers per hour, marking a significant milestone in the project.
Once fully operational, the East Container Terminal will be capable of handling some of the world's largest vessels, as well as import and transshipment containers. Its automated yard operations are designed to function with approximately 100 employees while adhering to international safety standards.
Senior officials of the Sri Lanka Ports Authority also participated in the inspection.